Foundation is blocked and covered with plastic, water lines are run, and the back (west) end of the foundation forms are set. Here are pix from this afternoon . . .
Monday, February 19, 2007
Sunday, February 18, 2007
lookin' good
With luck, maybe we'll see some concrete in the next week or so . . .
Guess we should make sure the kids arn't playing in there when they start pouring . . .
Guess we should make sure the kids arn't playing in there when they start pouring . . .
Tuesday, February 13, 2007
Thursday, February 08, 2007
more forms in place . . .
Starting to look like there might be a foundation in the near future. The entire foundation will be poured in 3 stages and should take about 6 weeks to complete. Here are more pics . . .
Tuesday, February 06, 2007
. . . and so it begins
Mark your calendars, February 6th - the forms are being set and a closing date of June 15 had been proposed (those guys are so funny!). Here are some pics . . .