Saturday, April 28, 2007

baby steps . . .

A little more progress toward completion of the upper slab (carport/entry). we're waiting for steel reinforcement, inspections, and another concrete pour. James said he hopes this will all happen this coming week . . . fingers are crossed!

Here are some more pics . . .

Front (east)


North Side


South Side


Back (West)

Thursday, April 19, 2007

More Forms and choices have been made (mostly) . . .

Progress continues on the forms and we had a good meeting with Julie to select (or reselect in some cases) our finish out material. The process was fun and kind of overwhelming - especially the exterior choices. I hope we made good decisions!

Are are some pics of the new forms - this will be our entry walk and carport slab . . .


Wednesday, April 18, 2007

Signs of more progress . . .

After a couple weeks of little activity, forms are being set for the 3rd and final phase of the foundation. Karen and I meet with Julie to make cabinet, floor and exterior color choices tomorrow morning.