Sunday, March 25, 2007

Giant Wall . . .

The have poured the back wall of the house and polished the concrete floor. Next, they'll seal (waterproof) the wall then set forms for the carport portion of the house. Here are some pix . . .



Tuesday, March 13, 2007

We Have Concrete!

Got an email from James (our building super) saying the 1st stage of foundation pour is scheduled for 7 AM today (Tuesday), we arrived about 7:30 and and they were well under way! Here are a few pix of the progress!

"Oh what a beautiful morning . . ."





60 yards (tons) of concrete later . . . smooth as glass . . .

Sunday, March 04, 2007

STEEL

Well, after a brief (relative) delay, the steel crew showed up and has installed the rebar inside the foundation forms and the electric guys have put up the temporary electric box. Here are a few pictures (sorry for the crappy quality) . . .